River Murray system annual operating plan - End October 2014 update

MDBA reports

River Murray system annual operating plan - End October 2014 update

The River Murray System Annual Operating Plan (Operating Plan) for the 2014-15 water year (1 June 2014 to 31 May 2015) was released in July 2014. The Operating Plan describes how the River Murray System may be operated under a number of assumed scenarios.

This document provides an update, as at end October 2014, of the six scenarios that were presented in the Operating Plan and should be used in conjunction with the original plan. The scenarios have been prepared by the Murray-Darling Basin Authority with input from the Australian Government and the States of New South Wales, Victoria and South Australia through MDBA's Water Liaison Working Group.